220KV power transmission line angle steel tower of Inner Mongolia electric power group Co., Ltd.
This project is a part of rural power network upgrading project, which is a most important driving force to boost domestic demand in recent years, especially when facing financial crisis. This project can not only optimize the relationship of power supply with power grids, but also can perfect the midwest rural power grids and power construction projects in places without electricity.
Located in Xilinhaote city, length of the line is 300 kilometers. Inner Mongolia electric power group Co., Ltd. invested in it, and our company took responsibility for the design, production, and installation. The project was completed in June 2013, this line overcame local’s problem of electricity use and unstable electricity, and also solved local’s living electricity problem.